Project: Beni Suef 4800MW Combined Cycle Power Plant 2

From 6, June, 2016 to 18, August,2017
Main Contractor: ELSEWEDY ELECTRIC-PSP.
Location: Beni Suif – Egypt.
Contractor: EL-soudi for Engineering Works

 

Scope OF Work

  • Installation of Firefighting Network.
  • Cast iron pipes.
  • Testing works.

 

EL-SOUDI Responsibility’s

  • Provide full supervision.
  • Provision of qualified manpower.
  • Provide hand tools for all manpower.
  • Provide HSE and PPE.
  • Provide diesel generators.
  • Provide Equipment, cranes, forklift, pickup, trucks …. etc.
  • Inspection quality control and inspection formats and manpower experience to undertake and monitor all QA/QC activation defined in this method statement and the company quality manual.